We had hoped to start this project in spring 2021, but the COVID pandemic has slowed down
our building schedule on the previous Cole Avenue project. We were able to complete the
excavation work and pour the frost walls in fall 2021, but then put the project on hold for the
winter. In spring 2022, the initial plumbing was completed, the foundation slab was poured and
we began framing in May 2022. The framing was completed and the roof shingled by November
2022 and we have added exterior insulation and exterior window trim while waiting for the
plumbing and electrical rough-in to be completed. We will move inside for the remainder of the
winter to work on interior insulation and sheetrock. Once warm weather returns, we will work
outside on the vinyl siding and continue work inside on flooring, trim and painting. We hope to
have the project completed by fall 2023.
Build Updates
Maple Street House
Project type
New Home
Construction start date
Status
Active
The second of two new homes being constructed on a lot at the corner of Cole Avenue and
Maple Street in Williamstown.We are using the same design as the Cole Avenue house with the
plans flipped east to west.